Jemena
Jemena distributes across north-west Melbourne. Its process is equipment-strict at both ends: an inverter that is not on Jemena’s own approved list cannot be connected or commissioned, and the system exports only at a low static limit until Jemena has finished its own remote testing and commissioning, then drops back to it if the inverter goes offline.
Who they supply
North-west Melbourne.
Jemena — Jemena Electricity Network · checked 2026-11-12
Network area checkJemena publishes no address check of its own. Ausgrid’s postcode check answers for Victorian postcodes as well as NSW, ACT and Queensland ones, including those that return more than one network.
Jemena’s edges meet three other networks. Ausgrid’s check returns CitiPower and Jemena for some inner-north postcodes, Powercor and Jemena for some in the west, and Powercor, AusNet Services and Jemena together for at least one on the northern fringe, because distribution boundaries run down streets rather than around postcodes. Confirm the network from the bill or the NMI record before an application is opened. Ausgrid — network area check
What they assess
- Two inverter lists, both checked
- The inverter must be on the Clean Energy Council’s CSIP-AUS compliant list and on Jemena’s own approved list. Jemena states that an inverter not on its list cannot connect to or be commissioned on its network.
- Pre-approval where needed, commissioning to close
- An Approve My Generation or Battery Storage application goes in before installation where the job needs one. A Commission My Inverter application through My Portal closes the job.
- Installed at a low static export limit
- The inverter goes in on the region setting the page names, with a low static export limit the page states. On a site with existing solar, the old inverters are either upgraded to CSIP-AUS compliant ones or held at that same low static limit.
- Commissioning evidence is gathered on site
- The inverter is registered through the manufacturer’s portal and its LFDI obtained, and a Licensed Electrical Inspector signs off and issues the CES. The Commission My Inverter application carries photos of the inverter settings and the static export limit, with the CES, the LFDI and the NMI. The inverter is left on and online so Jemena can do its part.
- Jemena’s testing is its own phase
- Jemena tests the system remotely before commissioning it. The higher export limit applies only once that has succeeded; until then the low static limit stays.
Where it snags
Applications up to the size the page states are rejected if the inverter is not on Jemena’s approved list, and the list is checked at the Commission My Inverter stage too. The wrong model does not surface as a question; it surfaces as a rejection after the work is done. Jemena adds to the list as it tests more manufacturers, so check it when the equipment is ordered. Jemena — solar installer support hub
From 1 November 2026, inverters for new installations must be CSIP-AUS 1.2 compliant. Jemena’s own pages do not say so yet; United Energy states the requirement applies to all Victorian electricity distribution businesses. Check the Clean Energy Council’s CSIP-AUS list as well as Jemena’s approved list before ordering, and treat an older model as needing the manufacturer’s confirmation first. United Energy — new CSIP-AUS 1.2 requirements from 1 November 2026
A rejected Commission my CSIP-Aus form means the AC and DC switches go off until the inverter’s AS 4777.2 settings are fixed and a new form is resubmitted. The customer is left with a system switched off, not one exporting at a reduced limit, so get the settings photos right the first time. Jemena — solar installer support hub
The inverter has to stay online. If Jemena cannot reach it, export is cut to the low limit the page states, which makes the customer’s internet a live part of the install rather than a convenience. Show them how to check and reconnect it at handover, and tell them there may be planned testing for ongoing compliance, because the consequence arrives months later and looks like a fault. Jemena — solar installer support hub
Where the meter needs reconfiguring, the service order goes through the customer’s chosen retailer. If the site is not reconfigured, the meter does not record exported energy and the customer receives no feed-in credits, which reads to them as the system not working. Jemena — solar installer support hub
Whether a battery brings the site into the backstop depends on how it is coupled. Jemena’s exemption table treats a new AC-coupled battery on its own as a non-backstop application, but a DC-coupled battery sharing a new hybrid inverter with solar makes both of them backstop jobs. A battery added where the existing solar was approved from 1 October 2024 and is not backstop enabled may have its export limited until that solar is commissioned for the backstop. Jemena — Victoria’s emergency backstop mechanism
The emergency backstop is the question customers ask after the sale, not before it. In a minimum system load event Jemena is directed by AEMO to reduce solar exports, and may switch systems off briefly. Explaining that it is a network-wide arrangement rather than a fault in their system saves the call-back. Jemena — Victoria’s emergency backstop mechanism
Go straight to
- My PortalThe pre-approval, where needed, and the Commission My Inverter application are both lodged here.
- Installer troubleshooting guideJemena’s own guide to what goes wrong in the portal and on site.
- Victoria’s emergency backstopThe exemption table for battery and solar combinations, and the explanation to hand a customer asking why their system was curtailed.
Confirm the distributor from the bill, NMI record or connection approval before relying on this page. Embedded networks, remote grids and private networks may use a different authority. The connection offer and the site-specific approval override anything general, here or on the distributor’s own site. Reviewed 2026-09-28.
All network authorities