AusNet Services
AusNet distributes electricity across eastern and north-eastern Victoria and Melbourne’s north and east. Its EnergyConnect portal issues an automatic pre-approval with the export limit attached, and closes the job too: the system must be emergency backstop enabled, and the post-installation form cannot be lodged until commissioning has returned a successful result.
Who they supply
Eastern and north-eastern Victoria, and Melbourne’s north and east.
AusNet — what we do · checked 2026-11-19
Network area checkAusNet publishes no address check of its own; the map on its own page is an image. Ausgrid’s postcode check answers for Victorian postcodes as well as NSW, ACT and Queensland ones, including those that return more than one network.
AusNet’s Melbourne edges meet three other networks. Ausgrid’s check returns AusNet Services and United Energy together for some outer-eastern postcodes, and Powercor, AusNet Services and Jemena together for at least one on the northern fringe, because distribution boundaries run down streets rather than around postcodes. Confirm the network from the bill or the NMI record before an application is opened. Ausgrid — network area check
The name covers more than one network. AusNet also runs Victoria’s state-wide electricity transmission network and a gas distribution network in western Melbourne, Geelong and parts of western Victoria. Neither is a guide to where it distributes electricity, so a western Victorian site with an AusNet gas bill is not, on that evidence, an AusNet solar connection. AusNet — what we do
What they assess
- Pre-approval before installation
- Approval is required before installation starts, and it comes from EnergyConnect: submit the application and the pre-approval is generated with the approved generation and export limit. An installer applying for a customer needs the customer’s permission to accept offers on their behalf.
- Automatic first, paid assessment second
- Where the automatic offer does not suit the system, the preferred specifications go in and the application continues as a paid manual assessment. Asking for more than the pre-approved offer, more capacity per phase than the page states, or a generation type the automatic path does not cover all take that route.
- Emergency backstop is a condition of connection
- Systems under the size the page states must be emergency backstop enabled through a CSIP-AUS compliant software communications client, compatible with AusNet’s utility server and on its approved inverter list. Power quality response modes (volt-var and volt-watt) must be in place as well.
- Close-out happens in the portal
- Within the window the page states, the post-installation form is completed in EnergyConnect: the inverter commissioned, what was installed confirmed, and the electrical works request, the Certificate of Electrical Safety and every inverter and battery serial number submitted. AusNet passes that data to AEMO’s national DER register, so an error there travels.
- Meter reconfiguration goes through the retailer
- The meter reconfiguration request goes to the customer’s retailer, which sends AusNet the service order. A smart meter is reconfigured remotely; an analogue meter, or more than one meter to consolidate, needs a truck visit, and the retailer bills either.
Where it snags
Skipping pre-approval does not save a step, it buys a paid one. AusNet says a manual assessment may be required where the correct pre-approval process was not followed, as well as where an application is outside its standard terms. AusNet — manual assessment costs
The export offer belongs to the day it was issued. Pre-approved export limits are calculated from the capacity available on the substation at the time of application, and that capacity falls as more customers on the same substation install solar. A neighbour’s approval, or an old one for the same site, is not a quote for this job. AusNet — up to 30kW connections
Systems are sized on the combined inverter rating, solar and battery inverters together, not on panel ratings. Adding a battery inverter changes the size the application is assessed at. AusNet — up to 30kW connections
A pre-approval expires. The system has to be installed within the period the page states from the offer acceptance date; an extension is by negotiation with AusNet, and otherwise a lapsed approval means a new application. AusNet — up to 30kW connections
The post-installation form for a backstop-enabled system cannot be submitted until a successful commissioning result has come back. A system that cannot reach AusNet’s utility server needs an emergency backstop exemption, which holds it to a low fixed export limit, so a site without reliable internet is a conversation for the quote. AusNet — up to 30kW connections
For a backstop-enabled device, AusNet’s configuration steps say not to apply a static export limit before commissioning. Firmware comes first, on a secure internet connection, and the system is registered through the manufacturer’s app or portal once installed. AusNet — smart inverter settings
From 1 November 2026, inverters for new installations must be CSIP-AUS 1.2 compliant. Check both the Clean Energy Council’s list and AusNet’s own approved list before ordering; being on one is not being on the other. AusNet — approved inverter list
Go straight to
- EnergyConnect portalPre-approval, the post-installation form and commissioning confirmation are all lodged here.
- Approved inverter listCheck equipment here before ordering. The page currently links the list as a PDF while the online version is upgraded.
- Smart inverter settingsAusNet’s configuration and registration steps, written for Victoria.
- Manual assessment costsWhat the paid path costs, worth knowing before quoting a site the automatic offer will not suit.
Confirm the distributor from the bill, NMI record or connection approval before relying on this page. Embedded networks, remote grids and private networks may use a different authority. The connection offer and the site-specific approval override anything general, here or on the distributor’s own site. Reviewed 2026-09-28.