NSW network

Endeavour Energy

Endeavour Energy distributes across Sydney’s Greater West, the Blue Mountains, the Southern Highlands, the Illawarra and the NSW South Coast. Its conditions fall on the installer and the equipment as well as the site: the installer must hold accreditation and a licence, the inverter has to clear a set of checks before it is bought, and the work follows the approved connection contract and its site-specific conditions.

Who they supply

Sydney’s Greater West, the Blue Mountains, the Southern Highlands, the Illawarra and the NSW South Coast.

Endeavour Energy — about us · checked 2026-09-18

  • Endeavour publishes a network capacity map searchable by postcode or feeder, aimed at development and at planning large-scale solar and battery storage. It reports available capacity in an area — it does not say which distributor supplies an address, and the regulator’s service-area link for this network currently lands there. For the which-network question, use a check that answers across all three NSW distributors. Endeavour Energy — network capacity map

What they assess

Permission to Connect is a named artefact
Approval is issued as a Permission to Connect, downloadable from the project in the Connections Portal. A solar retailer needs the reference number from an approved application to complete its own registration as an applicant in the NSW CER Installer Portal; approved jobs then pass into that portal, where the retailer allocates each one to an installer.
Several inverter gates, not one
Before it is bought, the unit must be CSIP-AUS compliant, meet the technical standard the page names and both parts of AS/NZS 4777, be configured to the network's own required inverter settings, and be listed by the Clean Energy Council or carry written network approval for that make and model — clearing the list does not clear the configuration.
The compliance certificate does not go to the network
The installer lodges the Certificate of Compliance for Electrical Work with Building Commission NSW, inside the deadline the page states; the network says it neither keeps solar certificates nor needs a copy. For eligible new and upgraded systems submitted and approved from 2 November 2026, the Installation Notification and the certificate go through the NSW CER Installer Portal instead, which the NSW Government says also covers the AEMO DER Register record, with device registration checks and capability testing phased in by postcode. The network's Connect supply or relocate assets page, under Connect a generator, still tells installers to enter the system on AEMO's register themselves, using the reference on the Permission to Connect letter — confirm which route the job is on.
The job can be audited after connection
The network audits some installations after connection, sometimes months later, and can disconnect an unsafe system immediately — the installation has to stand up to inspection long after the site is packed up.

Where it snags

  • An address outside the supply area fails silently in the portal: the site simply does not highlight on the map and no address row appears. There is no error explaining why, and the documented fallback is an email rather than a portal path — so treat an unresolvable address as a service-area question before assuming it is a form-filling problem. Endeavour Energy — Connections Portal user guide

  • Metering upgrades for a new solar installation sit with the retailer, not the network — the network's own responsibility table assigns them to the retailer. Treat the meter as a retailer service order to raise and confirm, not as something that follows automatically from approval. Endeavour Energy — your meter

  • Portal registration forks on a customer-type choice, and the accredited service provider path demands an accreditation number the retail path does not. Registration also completes multi-factor authentication against a mobile number, which makes a shared office account awkward to operate. Endeavour Energy — Connections Portal user guide

  • Pre-existing generation at the site has to be declared on the same application — the generator step asks for existing, new and removed capacity together, so a site with an earlier system is not a fresh application in the network's eyes. Endeavour Energy — Connections Portal user guide

  • Once an approved application has passed to the NSW CER Installer Portal, it can be amended or cancelled only while it sits there at ‘Awaiting Installation’ and before installation has started. Changes made in the Connections Portal flow through to the installer portal, and a cancellation cancels it there too — so an equipment change has to be settled before work starts. Endeavour Energy — how to submit a generator application

Go straight to

Confirm the distributor from the bill, NMI record or connection approval before relying on this page. Embedded networks, remote grids and private networks may use a different authority. The connection offer and the site-specific approval override anything general, here or on the distributor’s own site. Reviewed 2026-09-28.