QLD network

Ergon Energy Network

Ergon Energy Network distributes across regional Queensland — everything outside the south-east corner. It shares the Queensland connection manual with Energex and runs its own copy of the same Electrical Partners Portal, with its own forms.

What they assess

The installer's portal is a credential check
A retailer or installer applying for the customer lodges through the Electrical Partners Portal, and registering for it takes a current Queensland electrical contractor licence number or an accredited solar installer number. Customers can also apply themselves through a separate customer portal.
Three form types, and only one is right
The portal carries enquiries, connects and electrical work requests. A solar install that creates or changes a distributed energy record is a connect; the other two will not do the job.
Approval before installation, exporting or not
Every distributed energy system needs approval before it goes in, including systems configured never to export.

Where it snags

  • Energex and Ergon run the same portal under the same name, with the same form types, each on its own site — and an application form for one network is not interchangeable with the other. An application lodged with the wrong distributor is not considered and a new one is needed — so settle which network the NMI belongs to before logging in, not after. Ergon Energy Network — connection essentials

  • Picking the wrong form type costs a resubmission. An electrical work request is not a connect, and a solar job that creates or changes a distributed energy record needs the connect. The shared portal guidance, published on the Energex site, names both networks. Energex — portal user guides and tips

  • The job closes with a valid electrical work request through the portal once installation is complete — that is how the network is told the work was carried out to the required standards, so an install without one is not finished in the network's eyes. Ergon Energy Network — connection essentials

  • A high-voltage connected system leaves this pathway entirely and goes to the large customer connections group. Establish which side of that line a commercial job sits on before starting, because the two do not converge later. Ergon Energy Network — connection essentials

Go straight to

Confirm the distributor from the bill, NMI record or connection approval before relying on this page. Embedded networks, remote grids and private networks may use a different authority. The connection offer and the site-specific approval override anything general, here or on the distributor’s own site. Reviewed 2026-09-28.