Power and Water Corporation
Power and Water runs the Northern Territory’s networks: three regulated grids, smaller unregulated town networks and isolated community networks. In the main centres a basic connection passes through electrician, network and the customer’s retailer; in a remote community pre-approval comes first, because capacity is set community by community.
Who they supply
The Northern Territory, across separate systems rather than one grid: three regulated networks (the northern grid from Darwin to south of Katherine, the Tennant Creek grid and the southern grid around Alice Springs), smaller unregulated networks serving towns such as Daly Waters, Timber Creek and Elliott, and isolated networks in Aboriginal communities run through its subsidiary Indigenous Essential Services.
Power and Water — power networks and supply · checked 2026-11-22
Remote community solar capacityPower and Water publishes no address check, and the AER lists no Territory distributors. Its remote solar page lists each community and whether it is treated as part of the Darwin, Tennant Creek or Alice Springs grid, and links a retailer map showing where Power and Water is also the retailer.
Which system a site is on changes the job, not only the paperwork. Power and Water’s published connection types and limits are written for Darwin, Katherine, Alice Springs and Tennant Creek; for remote networks and minor centres it says customised requirements apply and to contact it first. Power and Water — inverter-based solar energy system requirements
In remote communities Power and Water generates, distributes and retails power, so there may be no separate retailer to deal with. In the main centres it distributes only and the customer buys from a retailer. Power and Water — about us
What they assess
- Banded by size, and by choice
- Inverter-based systems fall into basic, negotiated, large embedded generation and transmission connections, residential and commercial alike. A job becomes negotiated either because it falls outside the basic definition or because the applicant elects to negotiate the terms.
- Licensed and accredited, on the approved list
- Installers, battery installers included, need a current Northern Territory electrical licence and current Clean Energy Council design and installation accreditation, and all equipment must be on the CEC approved list. Approval from Power and Water comes before any work begins.
- Lodged by the electrician, by recommendation
- The network strongly recommends a licensed electrician or electrical contractor completes the application, because it asks for technical detail about the property, the installation and the proposed connection, and incomplete answers delay assessment.
- Assessment can pull the site into scope
- A technical assessment follows lodgement and may come back asking for more information or a property inspection rather than a straight yes, and depending on the location a pre-approval may also be needed.
- A connection agreement keeps it connected
- A PV inverter network connection agreement must be in place for the system to be connected and to stay connected, and it confirms the system complies with the network’s requirements.
Where it snags
Approval does not schedule the work. Once the network says the application can proceed, the customer has to contact their retailer, and the connection is only scheduled after the retailer’s request and all the documentation have arrived. A job that looks stalled after approval is usually waiting on the retailer step rather than on the network. Power and Water — basic connection
The paperwork after the work is part of the connection, not an afterthought. A Certificate of Compliance is what finalises it, and an embedded generation connection on the negotiated path also needs its commissioning documentation submitted. Power and Water — negotiated connections
The network charges the cost of connecting the meter to the retailer that raised the request, and the retailer may pass it on. Worth asking the retailer about before the customer is quoted a total. Power and Water — basic connection
A remote community job starts with a capacity question. Unlike rooftop solar in Darwin or Alice Springs, a new connection in a remote community needs pre-approval to confirm capacity is available, and the published per-community capacity is indicative and subject to change. Some communities have none. Where Power and Water is also the retailer, a power purchase agreement form and a commissioning sheet go in with the connection agreement. Power and Water — remote solar PV systems
An upgrade is a new application. Adding to an existing system goes through the same application process as a new one, not a variation of the old approval. Power and Water — solar power and battery energy storage systems
A sale voids the connection agreement. When the property is sold the existing network connection agreement becomes void and the new owner has to set up a new one, which is worth knowing when quoting work on a recently purchased home with solar already on the roof. Power and Water — solar power and battery energy storage systems
The meter may need replacing to manage export, and that runs on the network’s timeline once the documentation is in, longer again in remote communities. Tell the customer the system may be installed before it is exporting. Power and Water — solar power and battery energy storage systems
Go straight to
- Power connectionsThe pathway split between basic, negotiated and major connections.
- Inverter-based system requirementsConnection types, eligibility and the technical specifications for the main centres.
- Remote solar PV systemsThe remote application steps and the per-community capacity table.
- Connections resourcesApplication forms, the commissioning certificate and connection agreements for each pathway.
Confirm the distributor from the bill, NMI record or connection approval before relying on this page. Embedded networks, remote grids and private networks may use a different authority. The connection offer and the site-specific approval override anything general, here or on the distributor’s own site. Reviewed 2026-09-28.