VIC network

United Energy

United Energy covers Melbourne’s east and south-east suburbs and the Mornington Peninsula. It runs its own portal, myEnergy, and a named Solar Pre-Approval that expires. The close-out runs in a fixed order: backstop registration, a remote capability test, inspection, then the alteration request, and only after that is the approved export limit switched on.

Who they supply

Melbourne’s east and south-east suburbs and the Mornington Peninsula.

United Energy — who we are · checked 2026-11-12

Network area check

United Energy publishes no address check of its own. Ausgrid’s postcode check answers for Victorian postcodes as well as NSW, ACT and Queensland ones, including those that return more than one network.

  • The eastern edge meets AusNet Services. Ausgrid’s check returns both AusNet Services and United Energy for some outer-eastern postcodes, because distribution boundaries run down streets rather than around postcodes. Confirm the network from the bill or the NMI record before an application is opened. Ausgrid — network area check

  • The Victorian Government’s distributor list describes United Energy’s area as the southern suburbs and the Mornington Peninsula, without the eastern suburbs the network names itself. Neither description is a boundary; use the check and the NMI record. Victorian Government — find your energy distributor

What they assess

The Solar Pre-Approval is a named artefact
Pre-approval is required for every solar and battery installation. It is submitted through myEnergy before equipment goes in, and has to be approved and valid before anyone attends site.
Anyone can lodge it
The customer or a representative can apply: a solar retailer, an accredited installer, an REC or an LEW. The outcome goes by email to the customer, the applicant and any other parties the applicant nominates.
Three possible outcomes
Approved as applied for, approved at a lower export, or approved for self-consumption with no export. Most come back within minutes; one that needs a manual assessment takes longer and arrives by email.
Emergency backstop is a condition of connection
New, upgraded and replacement rooftop systems up to the size the page states must be emergency backstop enabled: able to communicate using CSIP-AUS and connected to the internet. The inverter is checked against the Clean Energy Council’s CSIP-AUS list and United Energy’s onboarded inverters list, and is installed with an export limiting meter.
Register, test, then close out
The inverter is registered through the manufacturer’s app, an LFDI is created and verified, and the registration is confirmed with United Energy. A capability test runs once the array is generating above the minimum the page states. A Licensed Electrical Inspector then inspects, and the alteration is submitted in myEnergy with the Certificate of Electrical Safety. The approved export limit is activated only after the alteration is completed and the paperwork validated.
The meter is reconfigured through the retailer
After the alteration, United Energy sends the paperwork to the customer’s retailer to request a service order, and reconfigures the meter once that order arrives.

Where it snags

  • The pre-approval expires. Let it lapse and a new pre-approval has to be obtained, which is the worst possible news to get after the system is already installed. The validity is stated on the help page and the approval itself; check it, because it is the kind of window that changes. United Energy — myEnergy help

  • Where the system or export sits outside the model standing offer, a generation deed is required, and it carries its own shorter signing deadline running from when the pre-approval issued. Miss it and the pre-approval expires. Two clocks, different lengths, both started by the same event. United Energy — myEnergy help

  • An alteration request can be refused for an invalid pre-approval before the pre-approval has expired. The usual cause is that it was never finalised: the generator agreement or the single-line diagram has not been uploaded to it, or what was uploaded was not valid, which shows as a Pending Action in myEnergy. United Energy — myEnergy help

  • A pre-approval can come back at a lower export, or with no export at all, because the outcome rests on the capacity of the neighbourhood network. United Energy says to factor that into the system size, so the outcome belongs in the quote rather than at handover. If capacity frees up later, it invites the applicant to reapply. United Energy — myEnergy help

  • Since 1 November 2026 an inverter model must be listed as CSIP-AUS 1.2 compliant on both lists, and one that is not can no longer be submitted through an alteration request in the portal. Batteries and vehicle-to-grid chargers under network control are caught too. An older model may get there by a firmware update, but that is the manufacturer’s question to settle before the job, not at close-out. United Energy — new CSIP-AUS 1.2 requirements from 1 November 2026

  • Register for myEnergy as the trade from the start. An REC, LEW or solar installer who does not answer ‘Yes’ to the electrician-or-installer question hits problems submitting applications, and converting a customer account to a trade account means de-registering it, which deletes any current applications on it. United Energy — myEnergy help

Go straight to

Confirm the distributor from the bill, NMI record or connection approval before relying on this page. Embedded networks, remote grids and private networks may use a different authority. The connection offer and the site-specific approval override anything general, here or on the distributor’s own site. Reviewed 2026-09-28.