Commissioning

Prove the whole control loop

An enabled setting is only one piece of commissioning evidence.

Prove the whole control loopFour linked evidence stages show approval, measurement, control and observed response. A return arrow connects observed response to measurement to represent feedback. No sensor orientation, wiring or numeric control value is specified.Approval1Measurement2Control3Response4
Evidence sequence, not a commissioning procedure or CT connection drawing. Follow the exact approved product process.
Explore the numbered points

POINT 1

Start with the approved intent

Record the approved arrangement, its connection point and every contributing inverter or battery. Do not substitute an inverter rating for the site limit.

POINT 2

Name what the controller sees

Keep meter or sensor identity, location, phase mapping, indicated direction and communications evidence. A plausible number can still describe the wrong point or phase.

POINT 3

Keep the as-found configuration

Record the requested limit, equipment state and every authorised change. Product-specific settings and wiring belong to the approved design and exact instructions.

POINT 4

Show what actually happened

Under the authorised commissioning process, retain named operating conditions and observed site flow. An enabled screen does not prove the complete response.

Use it in the field

FROM THE DIAGRAM TO THE JOB

Keep these checks with you.

  1. Identify the measurement chain

    Keep the site diagram, meter or CT model, controller, inverter and relevant firmware in the job record.

  2. Keep evidence sources separate

    Controller readings and independent meter evidence can use different update intervals, sign conventions and locations.

  3. Close with proof

    Record final settings, observed response, required communications-loss checks and the product's commissioning result.

Commissioning evidence connects the approval to the observed site response.

Read the guide's sources

Start a job record

Give it a job or site name. Wattbench will open the right evidence prompts.

Start job record
Sources listedReviewed September 2026Our methodology
Article details and scope
Topic
Export-control commissioning
Applies to
Grid-connected inverter energy systems
Audience
Licensed solar workers
Neutrality
Manufacturer-neutral
Read the full explainer
Key takeaways
  • Start with the approved site limit and point of application; do not infer either from the inverter rating.
  • The controller can only act on what its meter or CT arrangement reports, so direction, phase mapping, location and communications all need evidence.
  • A commissioning record should show settings as found, controlled test conditions and the measured response—not just a screenshot saying export control is enabled.

Begin with the approved intent

Export control starts with the connection approval, not the inverter menu. Record the approved export arrangement, the connection point it applies at, the phase arrangement and every inverter or battery that contributes to site generation. Network rules change and existing approvals may remain subject to the conditions under which they were assessed, so never replace the site record with a remembered “standard” limit.

The inverter's AS/NZS 4777.2 region or grid profile is part of the same approved intent. The network says which region applies and the manufacturer's manual says where it is set; the Grid Profile Settings Finder links each network's own settings page and each inverter family's menu path and profile names, without restating any setting value.

Western Power describes export limits as applying net at the network connection point. Its current guidance also says that changing an existing export or generation limit can trigger a new application. Other DNSPs use their own connection processes. The job pack therefore needs the actual approval and current DNSP requirements attached or referenced.

Treat the measurement chain as part of the control loop

A feed-in controller needs a trustworthy view of net site flow. Depending on the product, that view comes from a compatible energy meter, direct-connected measurement or current transformers. Record the meter and controller model, firmware, communications path, CT ratio where applicable, physical location, phase mapping and indicated direction.

Direction errors are especially deceptive: the interface may show plausible numbers while import and export signs are reversed. Multi-phase sites add another failure mode when a CT is mapped to the wrong phase. Do not correct wiring or settings from this article. Those are licensed-worker tasks performed from the exact product instructions and approved design.

Commission with controlled observations

Capture a baseline with generation, site load and grid flow clearly identified. Then create documented operating conditions that allow the control response to be observed without defeating protection or exceeding the approval. Compare the inverter or controller view, the site measurement and any independent meter evidence as separate sources; they can differ in update interval, sign convention and measurement point.

Record the requested limit, actual site flow, response time observed, equipment state and any communications loss behaviour. A single “enabled” screen does not prove that the complete measurement-and-control loop works.

What belongs in the evidence pack

  • Connection approval and approved export arrangement.
  • Single-line or site diagram identifying the measurement point.
  • Meter, CT, controller and inverter identifiers and firmware.
  • Settings as found and every authorised change.
  • Import/export observations under named operating conditions.
  • Final screenshots, test results and customer handover information.

Use the export-control commissioning playbook to collect the sequence and file the resulting evidence to a saved Wattbench job.

New to the jargon? Browse the glossary.

Sources

Best next action

Did this help you move the job forward?

Tell us what is missing
Good to know

Frequently asked

Is enabling an export-limit setting enough?
No. Commissioning needs evidence that the site meter or CT arrangement reports the correct direction and phases, communications remain available, and the complete system responds at the network connection point under controlled conditions.
Can Wattbench tell me the permitted export limit?
No. The authoritative value is the current approval and DNSP requirement for that connection. Wattbench records the value you have verified; it does not invent or substitute one.