Commission playbook
Export Control or Meter Commissioning Check
A field record for systems that export unexpectedly, remain capped or show implausible power-flow direction.
Safety boundaryRead first
Metering CTs, switchboards, export-control wiring and installer settings are licensed-worker tasks. Do not change limits without the approved connection details.
Safety boundary
Metering CTs, switchboards, export-control wiring and installer settings are licensed-worker tasks. Do not change limits without the approved connection details.
Field runner
Confirm the approved intentWork one stage at a time
Stage 1 of 30/9 checked
Confirm the approved intent
Evidence handoff
Keep the evidence with the job
These device-local checks are working state, not evidence. Save actual readings, observations and the outcome in a job record.
Start job recordView the complete procedure
01
Confirm the approved intent
- Record the approved export limit, phase arrangement and controlled equipment.
- Capture inverter, meter and controller make, model, firmware and settings as found.
- Preserve the connection approval and commissioning record.
02
Check the evidence
- Compare inverter flow, site meter flow and retailer data as separate measurement sources.
- Record import, export, load and generation under clear operating conditions.
- Check timestamps and identify any sign or direction mismatch.
03
Close the commissioning record
- Have CT orientation, phase mapping, communications and approved settings verified.
- Record every change and the before-and-after evidence.
- Retain the final test record and customer handover.
Source ledger3 sources